Task Name | % Complete | Start Date | Finish Date |
Phase II: Teacher Education Outcomes | 100% | Fri 5/19/06 | Fri 6/15/07 |
Develop Surveys | 100% | Fri 5/19/06 | Mon 11/20/06 |
1st year survey from Team 2 | 100% | Fri 5/19/06 | Fri 7/14/06 |
3rd year survey from Team 2 | 100% | Fri 9/22/06 | Fri 9/22/06 |
5th year survey from Team 2 | 100% | Mon 11/20/06 | Mon 11/20/06 |
Beginning Students survey from Team 2 | 100% | Thu 9/28/06 | Thu 9/28/06 |
Continuing Students survey from Team 2 | 100% | Mon 11/20/06 | Mon 11/20/06 |
Exiting Students survey from Team 2 | 100% | Tue 10/24/06 | Tue 10/24/06 |
Observer/Evaluator survey from Team 2 | 100% | Mon 10/16/06 | Mon 10/16/06 |
School-University Partnership survey from Team 2 | 100% | Wed 11/1/06 | Wed 11/1/06 |
Develop Survey Application | 100% | Fri 5/19/06 | Tue 10/3/06 |
Database | 100% | Fri 5/19/06 | Fri 5/19/06 |
Class to write out each type of question | 100% | Wed 9/13/06 | Tue 10/3/06 |
Build ASP skeleton | 100% | Wed 9/13/06 | Tue 10/3/06 |
Build Save & Load functionality | 100% | Mon 10/2/06 | Tue 10/3/06 |
Build JavaScript skip logic | 100% | Wed 9/13/06 | Tue 10/3/06 |
Navigation | 100% | Tue 10/3/06 | Tue 10/3/06 |
Encoding Surveys | 100% | Tue 8/29/06 | Fri 12/8/06 |
1st year survey pilot | 100% | Wed 10/4/06 | Mon 10/9/06 |
Ist year survey revisions | 100% | Fri 12/8/06 | Fri 12/8/06 |
3rd year survey | 100% | Mon 10/9/06 | Mon 10/9/06 |
5th year survey | 100% | Fri 12/8/06 | Fri 12/8/06 |
Beginning Students Survey | 100% | Mon 10/16/06 | Wed 10/25/06 |
Continuing Students Survey | 100% | Tue 8/29/06 | Wed 9/20/06 |
Exiting Students Survey | 100% | Tue 11/7/06 | Tue 11/7/06 |
Term survey revisions | 100% | Fri 12/8/06 | Fri 12/8/06 |
Observer/Evaluator Survey | 100% | Wed 11/1/06 | Wed 11/1/06 |
School University Partnership Survey | 100% | Mon 11/6/06 | Mon 11/6/06 |
Management Page for Institutions | 100% | Mon 10/23/06 | Tue 12/5/06 |
Identify features | 100% | Mon 10/23/06 | Wed 10/25/06 |
Build Summary Page | 100% | Wed 11/1/06 | Fri 11/3/06 |
Build Customize Item Page | 100% | Mon 11/6/06 | Wed 11/8/06 |
Build Email Customization Page | 100% | Thu 11/9/06 | Thu 11/9/06 |
Build Output Pages | 100% | Fri 11/10/06 | Fri 11/10/06 |
Develop draft final and testing | 100% | Thu 11/30/06 | Mon 12/4/06 |
Testing | 100% | Tue 12/5/06 | Tue 12/5/06 |
Management Page for SCHEV | 100% | Wed 11/15/06 | Mon 12/11/06 |
Identify features | 100% | Mon 12/4/06 | Mon 12/4/06 |
Database and programming | 100% | Wed 11/15/06 | Tue 12/5/06 |
Develop test plans | 100% | Thu 12/7/06 | Fri 12/8/06 |
Testing | 100% | Mon 12/11/06 | Mon 12/11/06 |
Survey Testing | 100% | Wed 10/4/06 | Fri 12/15/06 |
Unit testing | 100% | Wed 10/4/06 | Thu 11/30/06 |
Integration testing | 100% | Mon 12/4/06 | Tue 12/5/06 |
Full application testing | 100% | Thu 12/14/06 | Fri 12/15/06 |
Survey Documentation | 100% | Thu 11/16/06 | Fri 6/15/07 |
Code Documentation | 100% | Thu 11/16/06 | Fri 6/15/07 |
Installation and Deployment | 100% | Mon 12/18/06 | Mon 12/18/06 |
Packaging for delivery | 100% | Mon 12/18/06 | Mon 12/18/06 |
Delivery to SCHEV | 100% | Mon 12/18/06 | Mon 12/18/06 |
Enhancements and Modifications | 100% | Thu 1/25/07 | Wed 2/28/07 |
Phase III - School Descriptors/ Performance Data | 100% | Fri 9/29/06 | Tue 11/21/06 |
Program Descriptors Questionnaire | 100% | Fri 9/29/06 | Thu 10/12/06 |
Draft survey from Team 3 | 100% | Fri 9/29/06 | Fri 9/29/06 |
Database & programming | 100% | Fri 9/29/06 | Thu 10/5/06 |
Develop draft final & testing | 100% | Fri 10/6/06 | Thu 10/12/06 |
Teaching and Learning Conditions Survey | 100% | Wed 11/1/06 | Tue 11/21/06 |
Draft Survey from Team 3 | 100% | Wed 11/1/06 | Mon 11/6/06 |
Database & programming | 100% | Tue 11/7/06 | Mon 11/13/06 |
Incorporate into Teacher Surveys | 100% | Tue 11/14/06 | Tue 11/21/06 |
Phase IV - Reporting, Analysis, and Systems Support | 100% | Fri 6/9/06 | Fri 2/9/07 |
Standard reports | 100% | Mon 10/2/06 | Fri 12/29/06 |
Title II Supplemental Report | 100% | Mon 10/2/06 | Wed 12/20/06 |
Obtain report specifications | 100% | Mon 10/2/06 | Wed 10/18/06 |
Identify relevant data elements | 100% | Thu 10/19/06 | Fri 10/20/06 |
Develop wireframes and prototypes | 100% | Mon 10/23/06 | Wed 11/15/06 |
Develop additional data files | 100% | Thu 11/16/06 | Mon 11/27/06 |
Internal testing | 100% | Mon 11/27/06 | Wed 11/29/06 |
Deliver draft final reports to Leadership Team | 100% | Thu 11/30/06 | Wed 12/6/06 |
Incorporate feedback into system and test | 100% | Thu 12/14/06 | Wed 12/20/06 |
Title II Appendix C Report | 100% | Mon 10/2/06 | Wed 12/20/06 |
Obtain report specifications | 100% | Mon 10/2/06 | Wed 10/18/06 |
Identify relevant data elements | 100% | Thu 10/19/06 | Fri 10/20/06 |
Develop wireframes and prototypes | 100% | Mon 10/23/06 | Wed 11/15/06 |
Develop additional data files | 100% | Thu 11/16/06 | Mon 11/27/06 |
Internal testing | 100% | Mon 11/27/06 | Wed 11/29/06 |
Deliver draft final reports to Leadership Team | 100% | Thu 11/30/06 | Wed 12/6/06 |
Gather feedback from Leadership Team | 100% | Thu 12/7/06 | Wed 12/13/06 |
Incorporate feedback into system and test | 100% | Thu 12/14/06 | Wed 12/20/06 |
DOE Reports | 100% | Mon 10/2/06 | Wed 12/20/06 |
Biennial Targets Report | 100% | Mon 10/2/06 | Wed 12/20/06 |
Obtain report specifications | 100% | Mon 10/2/06 | Wed 10/18/06 |
Identify relevant data elements | 100% | Thu 10/19/06 | Fri 10/20/06 |
Develop wireframes and prototypes | 100% | Mon 10/23/06 | Wed 11/15/06 |
Develop additional data files | 100% | Thu 11/16/06 | Mon 11/27/06 |
Internal testing | 100% | Mon 11/27/06 | Wed 11/29/06 |
Deliver draft final reports to Leadership Team | 100% | Thu 11/30/06 | Wed 12/6/06 |
Gather feedback from Leadership Team | 100% | Thu 12/7/06 | Wed 12/13/06 |
Incorporate feedback into system and test | 100% | Thu 12/14/06 | Wed 12/20/06 |
Career Switchers Report | 100% | Mon 10/2/06 | Wed 12/20/06 |
Obtain report specifications | 100% | Mon 10/2/06 | Wed 10/18/06 |
Identify relevant data elements | 100% | Thu 10/19/06 | Fri 10/20/06 |
Develop wireframes and prototypes | 100% | Mon 10/23/06 | Wed 11/15/06 |
Develop additional data files | 100% | Thu 11/16/06 | Mon 11/27/06 |
Internal testing | 100% | Mon 11/27/06 | Wed 11/29/06 |
Deliver draft final reports to Leadership Team | 100% | Thu 11/30/06 | Wed 12/6/06 |
Gather feedback from Leadership Team | 100% | Thu 12/7/06 | Wed 12/13/06 |
Incorporate feedback into system and test | 100% | Thu 12/14/06 | Wed 12/20/06 |
TEAC Reports | 100% | Mon 10/2/06 | Wed 12/20/06 |
Obtain report specifications | 100% | Mon 10/2/06 | Wed 10/18/06 |
Identify relevant data elements | 100% | Thu 10/19/06 | Fri 10/20/06 |
Develop wireframes and prototypes | 100% | Mon 10/23/06 | Wed 11/15/06 |
Develop additional data files | 100% | Thu 11/16/06 | Mon 11/27/06 |
Internal testing | 100% | Mon 11/27/06 | Wed 11/29/06 |
Deliver draft final reports to Leadership Team | 100% | Thu 11/30/06 | Wed 12/6/06 |
Gather feedback from Leadership Team | 100% | Thu 12/7/06 | Wed 12/13/06 |
Incorporate feedback into system and test | 100% | Thu 12/14/06 | Wed 12/20/06 |
NCATE Reports | 100% | Mon 10/2/06 | Wed 12/20/06 |
Obtain report specifications | 100% | Mon 10/2/06 | Wed 10/18/06 |
Identify relevant data elements | 100% | Thu 10/19/06 | Fri 10/20/06 |
Develop wireframes and prototypes | 100% | Mon 10/23/06 | Wed 11/15/06 |
Develop additional data files | 100% | Thu 11/16/06 | Mon 11/27/06 |
Internal testing | 100% | Mon 11/27/06 | Wed 11/29/06 |
Deliver draft final reports to Leadership Team | 100% | Thu 11/30/06 | Wed 12/6/06 |
Gather feedback from Leadership Team | 100% | Thu 12/7/06 | Wed 12/13/06 |
Incorporate feedback into system and test | 100% | Thu 12/14/06 | Wed 12/20/06 |
Mail Merge File | 100% | Mon 10/2/06 | Wed 11/29/06 |
Obtain report specifications | 100% | Mon 10/2/06 | Wed 10/18/06 |
Identify relevant data elements | 100% | Thu 10/19/06 | Fri 10/20/06 |
Develop wireframes and prototypes | 100% | Mon 10/23/06 | Wed 11/15/06 |
Develop additional data files | 100% | Thu 11/16/06 | Mon 11/27/06 |
Internal testing | 100% | Mon 11/27/06 | Wed 11/29/06 |
Deliver final reports to SCHEV & support upload | 100% | Fri 12/29/06 | Fri 12/29/06 |
Dynamic report (TPA Validation Check) | 100% | Fri 9/29/06 | Tue 10/17/06 |
Draft requirements from SCHEV | 100% | Fri 9/29/06 | Fri 9/29/06 |
Programming | 100% | Mon 10/2/06 | Tue 10/17/06 |
Send to SCHEV | 100% | Tue 10/17/06 | Tue 10/17/06 |
Dataset Cutting Tool | 100% | Fri 6/9/06 | Thu 12/28/06 |
Requirements and Specifications | 100% | Fri 6/9/06 | Fri 9/29/06 |
Identify features | 100% | Fri 6/9/06 | Mon 8/21/06 |
Develop use cases | 100% | Wed 8/23/06 | Fri 8/25/06 |
Share documents with Team 4 | 100% | Fri 8/25/06 | Fri 8/25/06 |
Develop wireframes | 100% | Mon 8/28/06 | Mon 9/11/06 |
Obtain feedback on wireframes | 100% | Fri 8/25/06 | Fri 8/25/06 |
Functional Specifications | 100% | Mon 8/28/06 | Mon 8/28/06 |
Prototype | 100% | Thu 9/14/06 | Fri 9/29/06 |
Database design | 100% | Tue 9/5/06 | Fri 9/8/06 |
First Round: Institutional user w/ primary data cut, Access output | 100% | Wed 9/20/06 | Fri 10/6/06 |
Login and user selection process | 100% | Wed 9/20/06 | Fri 10/6/06 |
Summary page | 100% | Wed 9/20/06 | Fri 10/6/06 |
Primary dataset selection | 100% | Wed 9/20/06 | Fri 10/6/06 |
Variable selection | 100% | Wed 9/20/06 | Fri 10/6/06 |
Access output file | 100% | Wed 9/20/06 | Fri 10/6/06 |
Testing | 100% | Wed 9/20/06 | Fri 10/6/06 |
Second Round: Expand access levels, add CSV and HTML output | 100% | Tue 10/24/06 | Mon 11/20/06 |
Additional logins | 100% | Tue 10/24/06 | Mon 11/6/06 |
Select institutions | 100% | Tue 10/24/06 | Mon 11/6/06 |
CSV and HTML output files | 100% | Tue 10/24/06 | Mon 11/6/06 |
Testing concurrent with development | 100% | Tue 11/7/06 | Wed 11/15/06 |
Testing after development is complete | 100% | Thu 11/16/06 | Mon 11/20/06 |
Third Round: Additional datasets, add SAS output, admin console for SCHEV | 100% | Wed 11/15/06 | Tue 12/19/06 |
Additional datasets | 100% | Thu 11/16/06 | Mon 12/4/06 |
Find variable feature | 100% | Thu 11/16/06 | Mon 11/27/06 |
Save command, show command history, regenerating output file | 100% | Tue 12/12/06 | Thu 12/14/06 |
SAS output file | 100% | Tue 12/12/06 | Mon 12/18/06 |
SPSS output files | 100% | Thu 11/16/06 | Mon 11/27/06 |
Admin console & data dictionary | 100% | Wed 11/15/06 | Tue 12/19/06 |
Planning | 100% | Thu 11/16/06 | Thu 11/16/06 |
GUI Design and Layout | 100% | Wed 11/15/06 | Wed 11/15/06 |
Programming | 100% | Wed 12/13/06 | Tue 12/19/06 |
Testing concurrent with development | 100% | Thu 11/16/06 | Wed 11/29/06 |
Testing after development is complete | 100% | Thu 11/16/06 | Mon 11/20/06 |
User instructions and help file | 100% | Wed 12/13/06 | Fri 12/15/06 |
Incorporate testing feedback | 100% | Tue 11/21/06 | Tue 11/28/06 |
Documentation | 100% | Mon 12/18/06 | Thu 12/28/06 |
Convert survey data to DCT | 100% | Tue 11/21/06 | Mon 11/27/06 |
Provision of training and technical assistance for VACTE institutions | 100% | Mon 11/6/06 | Fri 11/10/06 |
Enhancements and Modifications | 100% | Thu 1/25/07 | Fri 2/9/07 |
Administration, Management, and other Tasks | 100% | Thu 6/15/06 | Tue 12/12/06 |
Steering Committee Meetings | 100% | Thu 6/15/06 | Tue 12/12/06 |
June meeting | 100% | Thu 6/15/06 | Fri 6/16/06 |
July meeting | 100% | Thu 7/20/06 | Fri 7/21/06 |
August teleconference | 100% | Wed 8/23/06 | Wed 8/23/06 |
September meeting | 100% | Thu 9/21/06 | Thu 9/21/06 |
December meeting | 100% | Tue 12/12/06 | Tue 12/12/06 |